Measuring Progress

Update published on LinkedIn  12-Aug-14

How do you know how much work have you completed of what you planned ?

There are three ways of doing it :

(1) Physical – Its a guesstimate, when nothing is available we use this

(2) Duration – (Time elapsed + Time left) is compared against Planned duration

(3) Units – (Effort spent + Effort left) is compared against Planned effort expressed in units.

Although this looks simple , it becomes complex where we have to deal with large number of activities.

Deciding this beforehand saves time & effort in updating the information and delivering accurate reports.

Please  share your thoughts

 

Percent Complete Type

Relevance : Primavera Project Planning, P6 Project Planning , Engineering Consultancy